Scheduled time period
Thursday 14th November 2024 at 6:00am to Saturday 16th November 2024 at 6:00amCulzean back to normal rates.
Unavailable Capacity
0GWh/d
Available Capacity
140GWh/d
Technical Capacity
140GWh/d
Related Remits
Below is a list of the other remits that belong to the same event as the remit above.
Scheduled time period
Thursday 14th November 2024 at 6:00am to Saturday 16th November 2024 at 6:00amCulzean ramp up ongoing and full rates expected by gas-day 16th November.
Unavailable Capacity
52GWh/d
Available Capacity
88GWh/d
Technical Capacity
140GWh/d
Scheduled time period
Thursday 14th November 2024 at 6:00am to Saturday 16th November 2024 at 6:00amCulzean ramp up ongoing and full rates expected by gas-day 16th November.
Unavailable Capacity
55GWh/d
Available Capacity
85GWh/d
Technical Capacity
140GWh/d
Scheduled time period
Thursday 14th November 2024 at 6:00am to Friday 15th November 2024 at 6:00pmCulzean has restarted and will continue to ramp up.
Unavailable Capacity
70GWh/d
Available Capacity
70GWh/d
Technical Capacity
140GWh/d
Scheduled time period
Thursday 14th November 2024 at 6:00am to Friday 15th November 2024 at 6:00pmCulzean restart is delayed.
Unavailable Capacity
118GWh/d
Available Capacity
22GWh/d
Technical Capacity
140GWh/d
Scheduled time period
Thursday 14th November 2024 at 6:00am to Friday 15th November 2024 at 6:00pmCulzean restart is delayed.
Unavailable Capacity
70GWh/d
Available Capacity
70GWh/d
Technical Capacity
140GWh/d
Scheduled time period
Thursday 14th November 2024 at 6:00am to Friday 15th November 2024 at 6:00amCulzean ESD testing is planned to start tomorrow morning. Rates will drop to half rates for 12 hours and then ramp up to full rates with 24 hours. Rates may vary during this time.
Unavailable Capacity
70GWh/d
Available Capacity
70GWh/d
Technical Capacity
140GWh/d