Impacted time period
Tuesday 5th November 2024 at 5:00am to Tuesday 12th November 2024 at 6:00amAlwyn close to pre-shutdown rates.
Unavailable Capacity
0mcm/d
Available Capacity
2.9mcm/d
Technical Capacity
2.9mcm/d
Related Remits
Below is a list of the other remits that belong to the same event as the remit above.
Impacted time period
Tuesday 5th November 2024 at 5:00am to Tuesday 12th November 2024 at 6:00amAlwyn restarted and ramp up will continue throughout the day with full rates expected by gas-day 12th November.
Unavailable Capacity
1.9mcm/d
Available Capacity
1mcm/d
Technical Capacity
2.9mcm/d
Impacted time period
Tuesday 5th November 2024 at 5:00am to Tuesday 12th November 2024 at 6:00amAlwyn restarted and ramp up will continue throughout the day with full rates expected by gas-day 12th November.
Unavailable Capacity
2.1mcm/d
Available Capacity
0.8mcm/d
Technical Capacity
2.9mcm/d
Impacted time period
Tuesday 5th November 2024 at 5:00am to Tuesday 12th November 2024 at 6:00amAlwyn restart ongoing, ramp up will continue throughout the day.
Unavailable Capacity
2.4mcm/d
Available Capacity
0.5mcm/d
Technical Capacity
2.9mcm/d
Impacted time period
Tuesday 5th November 2024 at 5:00am to Monday 11th November 2024 at 6:00pmAlwyn gas export stopped due to issue on oil export route. Restart currently unknown
Unavailable Capacity
2.9mcm/d
Available Capacity
0mcm/d
Technical Capacity
2.9mcm/d
Impacted time period
Tuesday 5th November 2024 at 5:00am to Friday 8th November 2024 at 6:00pmAlwyn gas export stopped due to issue on oil export route. Restart currently unknown
Unavailable Capacity
2.9mcm/d
Available Capacity
0mcm/d
Technical Capacity
2.9mcm/d
Impacted time period
Tuesday 5th November 2024 at 5:00am to Wednesday 6th November 2024 at 6:00pmAlwyn gas export stopped due to issue on oil export route.
Unavailable Capacity
2.9mcm/d
Available Capacity
0mcm/d
Technical Capacity
2.9mcm/d
Impacted time period
Monday 4th November 2024 at 10:00pm to Tuesday 5th November 2024 at 6:00pmAlwyn gas export stopped due to issue on oil export route.
Unavailable Capacity
1.4mcm/d
Available Capacity
0.5mcm/d
Technical Capacity
1.9mcm/d