Scheduled time period

Sunday 21st July 2024 at 10:00pm to Saturday 17th August 2024 at 12:00pm

Perenco Bacton throughput to ramp up during morning of the 17th. Current flows of 1.6 MCM/d.

Planned onshore maintenance & planned offshore production outage.

Unavailable Capacity
3.5mcm/d
Available Capacity
6.5mcm/d
Technical Capacity
10mcm/d