This is not the latest revision of this event. Please click here to see the latest update.

Scheduled time period

Monday 20th March 2023 at 6:00am to Friday 19th May 2023 at 10:00am

Reduced Perenco Bacton terminal gas export.

Unplanned onshore transmission system unavailability. Onshore maintenance complete, PUK Bacton deliveries ramping up from 01:00 gas day 18th.

Unavailable Capacity
9.8mcm/d
Available Capacity
2.5mcm/d
Technical Capacity
12.3mcm/d
Further Information