This is not the latest revision of this event. Please click here to see the latest update.

Scheduled time period

Monday 20th March 2023 at 6:00am to Thursday 18th May 2023 at 6:00pm

Reduced Perenco Bacton terminal gas export.

Unplanned onshore transmission system unavailability. Pending onshore maintenance completion, PUK Bacton deliveries looking to ramp up 18:00 during gas day 18th

Unavailable Capacity
12.3mcm/d
Available Capacity
0mcm/d
Technical Capacity
12.3mcm/d
Further Information